Server hardware migration - 23/02/2017 (mccabe) |
---|
We are planning a migration of this server tomorrow (23th February) to better hardware. The exact time of the switchover cannot be confirmed until more of the data has been moved across, but it will happen sometime around 10am. On the run up to this migration there will be some disruption to services (mail, FTP, MySQL) in the morning but we will attempt to keep these to a minimum. However some disruption is needed in order to maintain data integrity while the changeover happens. We will update this announcement when the migration is happening, and when it is complete. |
Updated by Chris Yates on 22nd Feb 2017 @ 11:54am |
Server hardware migration - 23/02/2017 (mccabe) |
---|
This is now proceeding. |
Updated by Chris Yates on 23rd Feb 2017 @ 10:20am |
Server hardware migration - 23/02/2017 (mccabe) |
---|
This server will now be rebooted to complete the migration. |
Updated by Chris Yates on 23rd Feb 2017 @ 10:55am |
Server hardware migration - 23/02/2017 (mccabe) |
---|
This migration is now complete. |
Updated by Chris Yates on 23rd Feb 2017 @ 11:15am |